The final phase of works on the electro-traction substation Trebešica

The final phase of works on the electro-traction substation Trebešica

Works on the dismantling of the existing, procurement and installation of the new electric traction substation "Trebešica" are in the final phase, which implies the activities of technical reception of the facility and connection of the electrical substation to the network, after which it will be handed over to use.

After the completion of the public procurement procedure, at the end of 2015, the Contract was signed with the bidder who implemented the project according to the FIDIC Yellow Book according to the principle "Project and Build". The work began in August 2017, after the finalization and revision of the Main Project were completed and the construction permit was obtained.

Works on the construction and delivery of complex equipment were completed within a shorter period than foreseen, creating conditions for the withdrawal of 100% allocated funds from IPA funds in the previous year.

The project was implemented with the aim of modernizing rail transport by improving its efficiency and safety. Being a part of the Operational Program "Regional Development 2012-2013" 85% of the project is financed through the IPA funds of the European Union and 15% through the Capital budget.

The program is implemented by the Operational Structure for IPA Component III (OS), which consists of the following bodies: the Ministry of Sustainable Development and Tourism - the body responsible for the complete Program and Environmental Projects, then the Ministry of Transport and Maritime Affairs - the body in charge of transport projects and Directorate of Public Works as Implementing body in charge of contracting and carrying out projects.