Contract for Lot 1 - Design and construction of treatment plants wastewater in the municipality of Berane, was signed with total budget of € 6.101.739,29, while the contract for Lot 2 - Construction of sewerage network in the municipality of Berane signed in the amount of € 4.881.918,44. Funds for both projects are of financed by the European Union through the IPA funds (85%) and co-funded by the Government of Montenegro (15%).
Contract for Lot 1 includes the construction project for the plant for wastewater treatment and construction works, in accordance with FIDIC conditions of contract for design and construction works - Yellow Book. The deadline for completion is 30 months, while the period for the elimination of possible defects is 12 months.
Contract for Lot 2 includes construction of sewage network, in accordance with FIDIC conditions of contract for construction works - Red Book. The deadline for completion is 20 months, while the period for the elimination of possible defects is 12 months.
The subject of the Contract is the revision of the main design and supervision of works for the Contract "Design and construction of treatment plants wastewater in the municipality of Berane - Lot 1", as well as supervision of the works contract for "Reconstruction of the sewerage system in the municipality of Berane - Lot 2 ".